Lab 4040



Overview + Key Features
Our team has procured and installed a new 6’ fume hood with ANTEC controls in a scientific lab. We demoed 1 20’ section of casework with electrical and lab gasses in it and then built a 20’ wall in its location. We also added electrical power and wire mold were installed along with Co2 and LVAC drops for new incubators and BSC’s/ we also added Co2 and O2 to 2 other existing lab benches/ after the scope of work was completed we were asked to demo another section of case work and finish off the are for a new piece of equipment to sit. Existing wire mold was re worked and new power and data installed on the column for the equipment.
​Challenges
These were only marked up drawings with changing information as the work went on.
​Solution
Working closely with the client to give them what they need
End Result
Lab work is complete and equipment is moving in
Project Details
Location
Boston, MA
Architect
Vanderweil
Type
Construction Management